After
the building permit is issued, periodic inspections are necessary,
including, but not limited to the following:
- All
footings and foundations must be inspected before concrete is
poured and/or block walls, etc. are erected. (Footings must be
at least 42 inches below the grade line, which is considered the
normal frost line.)
- All
footings and foundations must be inspected after completion, before
backfilling and with all anchor bolts in place.
- All
underground plumbing, both sanitary and storm, must be inspected
before backfilling.
- All
rough framing must be inspected as soon as the exterior is enclosed,
but before the interior work is started. (This includes the installation
of rough plumbing and rough electrical)
- Insulation
to meet the minimum energy code must be installed and inspected
before being enclosed.
- Final
inspection, when work is completed, is required. Any totally new
construction will require a Certificate of Occupancy inspection,
and the issuance of a Certificate of Occupancy or Certificate
of Compliance before the building is occupied in whole or in part.
- Electrical
additions/alterations must be inspected by Common Wealth (349-3900) or the Middle Department Inspection
Agency (454-5191) for both a rough and final inspection and issue
their certificate before the final inspection can be made by the
Building Department. It is the owner’s or contractors responsibility
to contact these Fire Underwriters and have these inspections
made.
It
will be the owner’s or builder’s responsibility to be certain these
inspections are made as outlined above. to schedule these inspections,
you should call 964-8181.